Beaverton’s Allen Blvd. street maintenance overlay project is ahead of schedule and some street closures will occur sooner than originally expected.
Allen Blvd. Street Maintenance Overlay Project
Project limits: 300′ west of Hall Blvd. to Hwy 217 overpass
Overall project timing: July 12 thru July 25
The following is the updated list of street boundaries, activity and the dates the activities will be performed:
| Street Boundaries | Activity | Original dates | New dates |
|---|---|---|---|
Allen Blvd. – 200 feet west of Hall to King Blvd. |
Paving |
July 19 |
July 17 |
Allen Blvd. – 200 feet west of Hall to King Blvd. |
Paving |
July 20 |
July 18 |
Allen Blvd. – 200 feet west of Hall to King Blvd. |
Paving |
July 21 |
July 21 (same) |
Work will begin at 7 a.m. and be complete no later than 11 p.m. Throughout the project, at least one lane of Allen Blvd. will remain open to traffic (east and west bound) and traffic detours will be in place for street closures on adjoining streets. The public works crew will reopen lanes of traffic once the new asphalt has cured, depending on weather conditions.
Updated street closures and delays:
Hall Blvd. and Lombard Ave. at Allen Blvd. will be closed intermittently on July 17 and 18 as well as July 21, if necessary. All intersecting streets from Hall Blvd to King Blvd. will be closed to through traffic at Allen Blvd. Expect delays on Allen Blvd. and intersecting streets throughout the project timeline.
Bus stop closures:
Hall at Allen, northbound – bus stop 2267 (July 17 and 18)
Hall at Allen, southbound – bus stop 2266 (July 17 and 18)
Lombard at Allen, northbound – bus stop 3455 (July 17 and 18)
Lombard at Allen, southbound – bus stop 3454 (July 17 and 18)
Bus stop delays, from July 12 through 25:
Allen at Hall, eastbound – bus stop 102
Allen at Hall, westbound – bus stop 103
Allen at Lombard, eastbound – bus stop 9687
Allen at King, eastbound – bus stop 9688
Allen at King, westbound – bus stop 9704
12200 block SW Allen, westbound – bus stop 9423
12200 block SW Allen, eastbound – bus stop 9424
See also: Allen Blvd Paving Project Ahead of Schedule
Questions about the paving project should be directed to the Public Works, Operations Office at (503) 526-2220, Debbie Martisak, Project Manager at (503) 350-4084 or Mark Olson, Paving Superintendent at (971) 246-0214.
As a reminder, train speeds along with corridor are permanently increasing. Expect a faster train at any time. Be safe. Always look both ways before crossing tracks. Always expect a train.
- Courtesy of TriMet -
More information: www.trimet.org/commuterrail/index.htm
The City of Beaverton provides the foregoing information as a public service. This information is collected from other sources and cannot be guaranteed as to accuracy or timeliness.