Project Description:

 Replace 200 feet of waterline with 4-inch ductile iron pipe and water service lines to addresses 7150 through 7180.
 


Project Manager:

L. Alan Johansson, 503-526-2792
 

Project Status:

 
FY16-17: Design by City staff.
FY16-17: Complete design. 
FY17-18: Complete construction by contract.
 

Substantial Completion Date:

June 30, 2018