Westgate Drive Intersection - CIP 3321

Westgate Drive/Cedar Hills Boulevard/Dawson Way Intersection Realignment



Project Description:

 Realign the intersection of Dawson Wy and Westgate Dr with Cedar Hills Blvd. Work includes intersection signalization, continuation of a 5-lane arterial cross section on Cedar Hills Blvd, and a 2-lane collector cross section on Westgate Dr and Dawson Wy. At the new intersection, street improvements on Westgate Dr and Dawson Wy include two twelve-foot through lanes, a left turn lane in each direction, and an eastbound right turn lane. Beyond the intersection, Dawson Wy and Westgate Dr will both be built within a 60 foot right of way and include two twelve-foot travel lanes with sharrows, eight-foot parking lanes, and 6'-10' sidewalks.

 Project Manager: Jim Brink, 503-526-2450
 

Project Status:

 FY11-12: Completed survey of Cedar Hills Blvd/Westgate Dr/Dawson Wy intersection.

FY12-13: Study alignment options. FY13-14: City staff begins preliminary design and budget estimates.

FY14-15: City staff continues preliminary design and budget estimates.

FY15-16: Contract with David Evans & Associates (DEA) approved 3-1-16. 3-16-16: NTP issued to DEA to begin design.

FY16-17: Submit land use applications, complete design, and begin ROW acquisition.

 

Substantial Completion Date:

  August 30, 2018