Farmington Rd - CIP 3302

Farmington Road (Hocken to Murray) MSTIP 3D



Project Description:

This is a Washington County MSTIP 3D project that proposes to widen 4200 feet of road to 5 lanes from Hocken Ave to Murray Blvd with bike lanes and sidewalks. Project also includes intersection improvements such as turn lanes at Hocken Ave and Murray Blvd and intersection realignment and signalization at the 141st Ave/142nd Ave intersection. Additional information on this project is available at http://www.beavertonoregon.gov/index.aspx?nid=1620 and http://www.co.washington.or.us/LUT/TransportationProjects/farmington-murray-to-hocken-project.cfm?page=About.

The estimated project cost for design, acquisition of right-of-way, and construction is $21.4 million. Washington County MSTIP will fund all aspects of the project except the water and sanitary sewer upgrades and utility undergrounding which will be funded by the City at an estimated cost of $ 2.7 million. The City staff is providing day to day project management and construction inspection.
  

Project Manager:

Ben Shaw, 503-526-2447

Project Status:

 FY12-13: In Mar 2012 Washington Co added project to MSTIP3D list. In Jan 2013 HHPRI was contracted by WASHCO to complete PS&E. 1-11-13 Project kickoff meeting. 4-10-13: Open House #1. Hold bi-weekly project development meetings. 6-3-13: Meeting with Central Beaverton NAC.

FY13-14: Continue design and begin ROW acquisition. 90% plans completed Aug 2013. 95% plans completed Dec 2013. PTF2013-0002 and SDM2013-0006 approved 12-31-2013. Eastbound right turn lane at Farmington/Murray removed 4-21-14. Open House #2 held 4-30-14.

FY14-15: Complete ROW acquisition, bid and award project, and begin construction. Site Development permit approved in Nov 2014. 100% plans approved Feb 2015. Open House #3 held 2-26-15. Bids opened 3-16-15. K&E Excavation of Salem, OR is the low bidder. Construction began 6-1-15.

FY15-16: Construction of south side roadway improvements and sanitary sewer improvements east of Murray Blvd.

FY16-17: Construction of north side roadway improvements and water improvements east of Murray Blvd and intersection improvements at Murray Blvd.
  
Night work will resume Oct. 9-13, and again Oct. 16-18 to install storm drains 

Weekend Work: is scheduled for Nov. 11-13 at the intersection of Farmington Rd and Murray Blvd (weather permitting). The weekend work is estimated to take place from 7 a.m. to 5 p.m. and flaggers will be present. The outside lanes on westbound and eastbound Farmington will be closed (blue section highlighted in traffic control plan, page 1). Vehicles and bicyclists are urged to use alternate routes such as TV Hwy and Allen Blvd. The weekend of Nov. 18-20, work will occur from 7 a.m. to 5 p.m. and the inside lanes on westbound and eastbound Farmington will be closed (highlighted in blue in traffic control plan, page 2), and left hand turns from westbound Farmington will be restricted.

Substantial Completion Date:

August 30, 2017

CIP 3302 Description
CIP_3302
CIP_3302_2